Wastewater Treatment Plant for Briceni
Tender: Feasibility study for wastewater treatment plant in Briceni
Implementation period: 2016
Implementing partner: TÜV Rheinland Česká republika s.r.o.
Financial resources provided by CzDA in 2016: 356 950 CZK
Tender: Camera survey of the sewage system in Briceni
Implementation period: 2017
Implementing partner: Lukáš Hladík
Financial resources provided by CzDA in 2017: 452 007,50 CZK
Tender: Preparation of project documentation for the construction of a wastewater treatment plant
Implementation period: 2018
Implementing partner: SHDP + G-servis (Sweco Hydroprojekt a.s., G-servis Praha spol. s r.o.)
Financial resources provided by CzDA in 2018: 2 500 000 CZK
Tender: Construction of a wastewater treatment plant in Bricemi
Implementation period: 2019-2023
Implementing partner: WWTP Briceni (Ircon, s.r.o., EKOSYSTEM spol. s r.o.)
Budget for the year 2019: 5 767 901,50 CZK
Budget for the year 2020: 25 379 555,37 CZK
Budget for the year 2021: 18 958 569,03 CZK
Planned budget for the year 2022: 3 866 912,41 CZK
Planned budget for the year 2023: 135 750,- CZK
Tender: Technical supervision for the construction of the wastewater treatment plant
Implementation period: 2020-2023
Implementing partner: Ion Scutari
Budget for the year 2020: 72 803,- CZK
Budget for the year 2021: 135 941,62 CZK
(planned) budget for the year 2022: 200 000,- CZK
(planned) budget for the year 2023: 85 715,- CZK
Tender: Author's supervision for the construction of a wastewater treatment plant
Implementing period: 2021-2023
Implementing partner: Sweco Hydroprojekt a.s.
Budget for the year 2021: 49 000,- CZK
(planned) budget for the year 2022: 364 955,- CZK
(planned) budget for the year 2023: 103 489,- CZK
Implementation period: 2016
Implementing partner: TÜV Rheinland Česká republika s.r.o.
Financial resources provided by CzDA in 2016: 356 950 CZK
Tender: Camera survey of the sewage system in Briceni
Implementation period: 2017
Implementing partner: Lukáš Hladík
Financial resources provided by CzDA in 2017: 452 007,50 CZK
Tender: Preparation of project documentation for the construction of a wastewater treatment plant
Implementation period: 2018
Implementing partner: SHDP + G-servis (Sweco Hydroprojekt a.s., G-servis Praha spol. s r.o.)
Financial resources provided by CzDA in 2018: 2 500 000 CZK
Tender: Construction of a wastewater treatment plant in Bricemi
Implementation period: 2019-2023
Implementing partner: WWTP Briceni (Ircon, s.r.o., EKOSYSTEM spol. s r.o.)
Budget for the year 2019: 5 767 901,50 CZK
Budget for the year 2020: 25 379 555,37 CZK
Budget for the year 2021: 18 958 569,03 CZK
Planned budget for the year 2022: 3 866 912,41 CZK
Planned budget for the year 2023: 135 750,- CZK
Tender: Technical supervision for the construction of the wastewater treatment plant
Implementation period: 2020-2023
Implementing partner: Ion Scutari
Budget for the year 2020: 72 803,- CZK
Budget for the year 2021: 135 941,62 CZK
(planned) budget for the year 2022: 200 000,- CZK
(planned) budget for the year 2023: 85 715,- CZK
Tender: Author's supervision for the construction of a wastewater treatment plant
Implementing period: 2021-2023
Implementing partner: Sweco Hydroprojekt a.s.
Budget for the year 2021: 49 000,- CZK
(planned) budget for the year 2022: 364 955,- CZK
(planned) budget for the year 2023: 103 489,- CZK
MD-2016-079-FO-14050
(IDENTIFIKAČNÍ ČÍSLO)
(IDENTIFIKAČNÍ ČÍSLO)
47 698 575 CZK
(CELKOVÝ PŘEDPOKLÁDANÝ ROZPOČET)
(CELKOVÝ PŘEDPOKLÁDANÝ ROZPOČET)
2016–2023
(DOBA REALIZACE)
(DOBA REALIZACE)
The town of Briceni has approached the Czech Republic with a request for cooperation in improving the quality of groundwater and surface water. The problems are mainly caused by inadequate wastewater management and an outdated sewerage network, much of which was built in the 1970s. Due to limited maintenance, wastewater leaks into the soil and groundwater. The project aims to construct a wastewater treatment plant as well as to reconstruct the pumping stations and the sewerage network.
The construction of the wastewater treatment plant for 5,000 equivalent inhabitants started in August 2019. On 28 February 2022, the newly constructed treatment plant was handed over to the beneficiary for operation, with a one-year test run commencing at the same time. In parallel, the main pumping station was technologically equipped, while the city financed the reconstruction of the outdoor part of the station.
The construction of the wastewater treatment plant for 5,000 equivalent inhabitants started in August 2019. On 28 February 2022, the newly constructed treatment plant was handed over to the beneficiary for operation, with a one-year test run commencing at the same time. In parallel, the main pumping station was technologically equipped, while the city financed the reconstruction of the outdoor part of the station.