Restoration of Waste Water Treatment System in Cimişlia
Tender: Restoration of waste water treatment system in Cimişlia
Implementation period: 2011 - 2017
Implementing partner: Consortium "Waste Water Treatment Cimişlia" (Ircon s.r.o., TopolWater s.r.o.)
Financial resources provided by CzDA in 2011: 4 800 000 CZK
Financial resources provided by CzDA in 2012: 6 797 000 CZK
Financial resources provided by CzDA in 2013: 4 638 000 CZK
Financial resources provided by CzDA in 2014: 287 000 CZK
Financial resources provided by CzDA in 2017: 51 000 CZK
Implementation period: 2011 - 2017
Implementing partner: Consortium "Waste Water Treatment Cimişlia" (Ircon s.r.o., TopolWater s.r.o.)
Financial resources provided by CzDA in 2011: 4 800 000 CZK
Financial resources provided by CzDA in 2012: 6 797 000 CZK
Financial resources provided by CzDA in 2013: 4 638 000 CZK
Financial resources provided by CzDA in 2014: 287 000 CZK
Financial resources provided by CzDA in 2017: 51 000 CZK
CzDA-MD-2011-5-14022
(IDENTIFIKAČNÍ ČÍSLO)
(IDENTIFIKAČNÍ ČÍSLO)
18 793 000 CZK
(CELKOVÝ PŘEDPOKLÁDANÝ ROZPOČET)
(CELKOVÝ PŘEDPOKLÁDANÝ ROZPOČET)
2011 - 2017
(DOBA REALIZACE)
(DOBA REALIZACE)
The subject of the development intervention is the services and technical assistance, which concludes in decrease in pollution from the waste waters and securing of the sustainable waste water treatment system in the town of Cimişlia in Moldova. The partner organization for this project is the municipal administration of Cimişlia (Primaria Cimişlia).
The essential construction works, which are not the part of the tender, will be coordinated with the municipal administration of Cimişlia. It will be responsible for these works, while it made a commitment to contribute to the project realization with the 20 % contribution through in-kind inputs (first of all, construction works).
The subject of the project is mostly the proposal of technical measures and ensuring the reconstruction of the STP and local pumping station, automatic system of operation management of system of pumping stations for waste waters, training of the employees, maintaining the technological part of the waste water treatment system and creation of the plan of long-term development for the APACANAL Cimişlia organization is conducting the educational campaign aimed at the population and industrial entities of the Cimişlia. All the construction documentation was finished in 2012, and the construction works have been started.
The essential construction works, which are not the part of the tender, will be coordinated with the municipal administration of Cimişlia. It will be responsible for these works, while it made a commitment to contribute to the project realization with the 20 % contribution through in-kind inputs (first of all, construction works).
The subject of the project is mostly the proposal of technical measures and ensuring the reconstruction of the STP and local pumping station, automatic system of operation management of system of pumping stations for waste waters, training of the employees, maintaining the technological part of the waste water treatment system and creation of the plan of long-term development for the APACANAL Cimişlia organization is conducting the educational campaign aimed at the population and industrial entities of the Cimişlia. All the construction documentation was finished in 2012, and the construction works have been started.